Try these 10 sample questions from the RCDD exam practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.

  1. 1An ICT designer needs a shared description of the project's major deliverables, assumptions, constraints, and required work. Which document serves this purpose?

    1. A. The project scope statement
    2. B. The project milestone schedule
    3. C. The project risk register
    4. D. The project cost estimate

    Answer: A

    Explanation: The DOE lexicon defines a scope statement as "A description of the project's scope which contains major deliverables, assumptions, constraints and a description of the work required to carry out the project." This establishes a common understanding of the required ICT work; a schedule, risk register, or cost estimate addresses a different planning dimension.

    Reference: Department of Energy — Project Management Lexicon of Terms — Scope Statement entry

  2. 2For a DoD ICT design following UFC 3-580-01, the schematic design analysis lists the systems in scope. What additional information belongs with those system listings?

    1. A. Only the selected manufacturers' warranty periods
    2. B. The final serial numbers of all installed components
    3. C. Points of contact for the listed systems
    4. D. Only the construction contractor's progress payments

    Answer: C

    Explanation: Table 2-2 states, "All ICT systems identified in the design scope should be listed with points of contact (POC) for systems." System contacts are part of this early coordination record; final serial numbers and payment records do not fulfill that requirement.

    Reference: UFC 3-580-01 — Information and Communications Technology Infrastructure Planning and Design — Table 2-2, DASD, p. 5

  3. 3A federal owner is preparing a negotiated acquisition for an ICT design. Under FAR 15.203, what is the RFP's function?

    1. A. Gather planning capability information without soliciting contract offers
    2. B. Obtain product submittal approval under an existing construction contract
    3. C. Communicate Government requirements and solicit contractor proposals
    4. D. Notify a successful offeror of the Government's binding contract acceptance

    Answer: C

    Explanation: FAR 15.203(a) says RFPs "communicate Government requirements to prospective contractors and ... solicit proposals." Planning-market inquiries, construction submittal approvals, and contract acceptance notices have different acquisition functions.

    Reference: FAR 15.203 — Requests for Proposals — FAR 15.203(a)

  4. 4What information must ICT shop drawings convey to demonstrate the proposed installation under FAR 52.236-21(d)?

    1. A. Overall equipment ratings without fabrication or attachment details
    2. B. General system relationships without component assembly or fit details
    3. C. Detailed fabrication, assembly, fit, and attachment information
    4. D. Standard product dimensions without the proposed installation interfaces

    Answer: C

    Explanation: Paragraph (d) describes shop drawings as showing proposed fabrication and assembly and "the installation (i.e., fit, and attachment details) of materials or equipment." Ratings, schematic relationships, and standard product dimensions alone omit the proposed detailed installation.

    Reference: FAR 52.236-21 — Specifications and Drawings for Construction — FAR 52.236-21(d)

  5. 5While defining an ICT upgrade, a designer finds that stakeholders have not agreed to include a proposed surveillance subsystem. How should that subsystem be classified in the current scope?

    1. A. Included because it uses the same cabling system
    2. B. Included because a supplier has provided pricing
    3. C. Outside the agreed scope until inclusion is agreed
    4. D. Outside the scope even after stakeholders approve it

    Answer: C

    Explanation: The Scope entry states, "Generally limited to that which is agreed to by the stakeholders in an activity or project (i.e., if not agreed to, it is out of scope.)." Shared infrastructure and available pricing do not themselves establish stakeholder agreement. Later agreement can change the scope.

    Reference: Department of Energy — Project Management Lexicon of Terms — Scope entry

  6. 6A DoD ICT designer prepares the interim design analysis after the approved 30% submission. Which submission approach meets UFC 3-580-01?

    1. A. Submit a fully updated analysis incorporating greater detail
    2. B. Submit only a list of changes to the 30% submission
    3. C. Resubmit the unchanged 30% analysis as the interim record
    4. D. Replace the analysis with the selected product data sheets

    Answer: A

    Explanation: Table 2-2 requires "an entirely updated analysis (not amendments to 30% submittal)" and says the earlier information must be included with more detail. A change list, unchanged analysis, or product sheets alone does not meet that requirement.

    Reference: UFC 3-580-01 — Information and Communications Technology Infrastructure Planning and Design — Table 2-2, DAID, p. 6

  7. 7What evaluation guidance must a competitive federal ICT RFP disclose under FAR 15.203(a)(4)?

    1. A. Evaluation factors, significant subfactors, and their relative importance
    2. B. Evaluation factors, with relative importance selected after proposal receipt
    3. C. Relative importance of price, with significant technical subfactors undisclosed
    4. D. Significant technical subfactors, with their relative importance left undisclosed

    Answer: A

    Explanation: FAR 15.203(a)(4) requires "Factors and significant subfactors that will be used to evaluate the proposal and their relative importance." Each competing disclosure omits or postpones a required part of that evaluation guidance.

    Reference: FAR 15.203 — Requests for Proposals — FAR 15.203(a)(4)

  8. 8Under adopted UFGS 27 10 00 requirements, what must ICT equipment wiring diagrams identify so interconnections can be coordinated?

    1. A. Identify circuit terminals, internal wiring, and interconnections between equipment
    2. B. Identify external ports and interconnections while omitting internal equipment wiring
    3. C. Show internal wiring while leaving interconnections between equipment unspecified
    4. D. List equipment circuit labels without showing terminals or wiring connections

    Answer: A

    Explanation: Section 1.6.1 states, "Wiring diagrams must identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment." Each other approach omits required terminal, internal-wiring, or interconnection information.

    Reference: UFGS 27 10 00 — Building Telecommunications Cabling System — Section 1.6.1, Shop Drawings, pp. 14–15

  9. 9Two ICT work packages have similar titles, and the designer must determine precisely which work is assigned to each WBS element. Which reference should the designer consult?

    1. A. The organizational breakdown structure
    2. B. The work breakdown structure dictionary
    3. C. The cumulative project expenditure curve
    4. D. The network activity relationship diagram

    Answer: B

    Explanation: The lexicon states, "A WBS dictionary defines the work scope for each element in the WBS." This is the element-level scope reference. Organizational assignments, expenditure curves, and activity relationships do not replace the definition of each element's work.

    Reference: Department of Energy — Project Management Lexicon of Terms — Work Breakdown Structure (WBS) Dictionary entry

  10. 10At the interim stage of a DoD ICT design, some applicable specification sections have not yet been edited. What does UFC 3-580-01 require in that specification submission?

    1. A. Omit unedited sections until the corrected final submission
    2. B. Replace unedited sections with equipment catalog pages
    3. C. List only edited sections so the submission appears complete
    4. D. List and include all applicable sections, even if unedited

    Answer: D

    Explanation: For SID, Table 2-2 directs, "List all applicable specifications and include even if unedited." The submission must disclose the applicable specifications rather than omit them or substitute catalog information.

    Reference: UFC 3-580-01 — Information and Communications Technology Infrastructure Planning and Design — Table 2-2, SID, p. 5

Topics in this practice bank

These topics describe the available practice for RCDD exam. Review the examination outline and its sources for scope and allocation details.

  • Define Scope of Project
    • Identify scope of work and client ICT requirements
    • Design for applicable codes, standards, client requirements and order of precedence
    • Estimate ICT project costs against performance and budget expectations
    • Estimate ICT project timeline against client time frame expectations
  • Design ICT Solutions
    • Produce ICT design project documentation
    • Locate and size ICT telecommunications spaces
    • Coordinate ICT design with other services
    • Coordinate work area outlet locations
    • Calculate ICT telecommunications space pathways
    • Specify ICT telecommunications space pathway types
    • Specify ICT work area outlet products
    • Specify ICT horizontal transmission media
    • Calculate ICT horizontal pathways
    • Specify ICT horizontal pathway types
    • Coordinate ICT horizontal pathways
    • Specify ICT OSP backbone transmission media
    • Calculate ICT OSP backbone pathways
    • Specify ICT OSP backbone pathway types
    • Coordinate ICT OSP backbone pathways
    • Specify ICT premise backbone transmission media
    • Calculate ICT premise backbone pathways
    • Specify ICT premise backbone pathway types
    • Coordinate ICT premise backbone pathways
    • Incorporate ICT telecommunications space system requirements
    • Advise the electrical engineer on telecommunications space requirements
    • Advise the mechanical engineer on HVAC and plumbing requirements
    • Specify ICT telecommunications space SCS components
    • Design ICT telecommunications spaces
    • Coordinate ICT telecommunications space pathways
    • Produce ICT design documents and bill/list of materials
    • Evaluate ICT design
    • Review ICT design documents with the client
    • Specify ICT grounding, bonding, lightning and surge protection
    • Specify ICT system administration and labeling
    • Specify ICT system testing
    • Specify ICT firestop and penetration requirements
  • Support ICT Bid/Tender Process
    • Generate ICT RFP or RFQ
    • Respond to ICT RFP or RFQ
    • Generate ICT RFI
    • Respond to ICT RFI
    • Review ICT proposals for completeness
    • Participate in additional bid/tender activities
  • Support ICT Installation Process
    • Produce ICT submittals for approval
    • Review ICT submittals
    • Revise ICT submittal
    • Participate in ICT materials procurement
    • Coordinate ICT installations with other services
    • Conduct ongoing ICT inspections
    • Conduct final ICT inspections
    • Produce ICT close-out documentation
    • Review ICT close-out documentation with the owner

How to use these free practice questions

Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.

These are independent study questions, not actual examination items. For examination requirements and official information, view RCDD exam details.