Try these 10 sample questions from the SAFe® Lean Portfolio Manager practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.

  1. 1A portfolio leadership team detects a market shift and rapidly implements a revised strategy. Which specific aspect of organizational agility does this demonstrate?

    1. A.Strategy agilityCorrect answer: A
    2. B.Lean business operations
    3. C.Lean-thinking people and Agile teams
    4. D.Learning organization

    Explanation: The portfolio management overview defines strategy agility as "the ability to sense changes in market conditions and implement new strategies quickly and decisively when necessary." This team is adjusting strategy in response to market change.

    Reference: Lean Portfolio Management Discipline — Portfolio Leadership and the Goal of Strategy Agility

  2. 2Portfolio leaders need to express enterprise strategic intent as measurable portfolio-level business objectives. Which construct provides this connection?

    1. A.Portfolio roadmap
    2. B.Strategic themesCorrect answer: B
    3. C.Portfolio backlog
    4. D.Portfolio canvas

    Explanation: The guidance states that "Strategic themes connect the enterprise strategy to a portfolio" and distill strategic factors into actionable, measurable goals.

    Reference: Strategic Themes — Details

  3. 3A proposed portfolio initiative needs coordination through the portfolio Kanban, including collaboration on its Lean business case and minimum viable product. Which role is responsible for shepherding it through that system?

    1. A.Business owner
    2. B.Product owner
    3. C.Epic ownerCorrect answer: C
    4. D.Release train engineer

    Explanation: The role definition states that "The Epic Owner is responsible for coordinating epics through the portfolio Kanban system." The article also describes collaboration on the business case and minimum viable product.

    Reference: Epic Owners — Definition

  4. 4Portfolio leaders want value streams to make local spending decisions within shared governance and spending policies. Which portfolio mechanism provides those policies?

    1. A.Portfolio vision
    2. B.Lean budget guardrailsCorrect answer: B
    3. C.Portfolio roadmap
    4. D.Strategic themes

    Explanation: The portfolio overview states that "Guardrails support these budgets by providing governance and spending policies and practices". They establish the policy context for value-stream spending.

    Reference: Lean Portfolio Management Discipline — Lean Budgets and Balancing Portfolio Investments

  5. 5A proposed initiative in the portfolio Kanban no longer advances the portfolio strategy. How should the portfolio handle this work item?

    1. A.Return it to the Kanban backlog
    2. B.Remove it from the Kanban systemCorrect answer: B
    3. C.Advance it to Kanban analysis
    4. D.Move it to Kanban implementation

    Explanation: The portfolio overview says "work items that don’t move forward in the portfolio strategy are removed from the Kanban system." An initiative no longer advancing the strategy should therefore be removed.

    Reference: Lean Portfolio Management Discipline — Lean Portfolio Management

  6. 6A portfolio wants an organizational function to facilitate portfolio management and foster operational excellence as its delivery model changes. Which function has this responsibility?

    1. A.Value Management OfficeCorrect answer: A
    2. B.Enterprise architecture
    3. C.Product management
    4. D.Release train engineering

    Explanation: The role definition describes the Value Management Office as "responsible for facilitating the Lean Portfolio Management process and for fostering operational excellence and lean governance" during a Lean-Agile transformation.

    Reference: Value Management Office (VMO) — Definition

  7. 7A portfolio leader wants a metric from the domain that measures how efficiently work is delivered. Which measure fits that domain?

    1. A.Customer satisfaction
    2. B.Employee engagement
    3. C.Flow timeCorrect answer: C
    4. D.Return on investment

    Explanation: The guidance says "Flow metrics assess delivery efficiency and predictability, including flow distribution, velocity, time, load, efficiency, and predictability." Flow time belongs to this domain; the other options are outcome measures.

    Reference: Measure and Grow — Summary

  8. 8An enterprise needs an integrated management discipline that connects strategy with execution through investment funding, operational coordination, and governance. Which discipline addresses that combination?

    1. A.Agile product delivery
    2. B.Lean portfolio managementCorrect answer: B
    3. C.Enterprise solution delivery
    4. D.Team and technical agility

    Explanation: The overview states that "The Lean Portfolio Management (LPM) Discipline aligns strategy and execution" by applying Lean and systems thinking across the specified activities.

    Reference: Lean Portfolio Management Discipline — Lean Portfolio Management

  9. 9Leaders want an aspirational description of the future state of the portfolio's value streams and solutions to guide investment decisions. Which artifact should they develop?

    1. A.Portfolio backlog
    2. B.Portfolio roadmap
    3. C.Portfolio visionCorrect answer: C
    4. D.Portfolio budget

    Explanation: The definition states, "The Portfolio Vision describes the future state of a portfolio’s value streams and solutions." It supplies the desired future state used to identify potential epics.

    Reference: Portfolio Vision — Definition

  10. 10An epic's MVP produces evidence that its hypothesis is not proven. Portfolio leaders want to invest further. Which work item must be created for that further investment?

    1. A.A new epicCorrect answer: A
    2. B.A new capability
    3. C.A new feature
    4. D.A new story

    Explanation: The portfolio overview states that when the hypothesis is not proven, "any further investment requires the creation of a new epic." The leaders should therefore establish a new epic for that further investment.

    Reference: Lean Portfolio Management Discipline — Manage Strategic Initiatives and Enhancing Portfolio Flow

Exam Review

About SAFe® Lean Portfolio Manager

SAFe® Lean Portfolio Manager · US

Key exam facts

Provider
Scaled Agile, Inc.
Format
Web-based, closed book, no outside assistance; multiple-choice, single-select
Exam questions
Total questions: 45.
Time limit
90 minutes
Passing score
77%
Exam fee
First attempt included in course registration fee within 60 days of completion; retake fee $50

Topics covered

The authority publishes percentage ranges for each content area. The practice percentages below use the midpoint of each range, normalized to 100%; they are not exact percentages published by the authority. Practice question counts may differ slightly because of rounding.

  • Introducing Lean Portfolio Management — Official range: 12–14% (Practice allocation: 13.4%)

    • The Purpose of SAFe® Lean Portfolio Management
    • The Lean-Agile mindset and SAFe® principles
    • Problems of project-cost accounting
    • Benefits of organizing around value
    • SAFe® portfolio structure
    • The Shift to Lean Portfolio Management
  • Establishing Portfolio Strategy and Vision — Official range: 14–16% (Practice allocation: 15.46%)

    • Connect the Portfolio to the Enterprise Strategy
    • Portfolio Vision
    • Portfolio Roadmap
  • Realizing Portfolio Vision Through Epics — Official range: 12–14% (Practice allocation: 13.4%)

    • Portfolio Epics
    • Epic Costs
    • Innovation through the SAFe® Lean Startup Cycle
  • Establishing Investment Funding — Official range: 16–18% (Practice allocation: 17.53%)

    • Lean Budget Guardrails
    • Strategic Portfolio Review and Portfolio Sync
    • Participatory Budgeting
    • Value Stream budgets
  • Managing Portfolio Flow — Official range: 16–18% (Practice allocation: 17.53%)

    • Flow with the Portfolio Kanban
    • Epic implementation with WSJF
  • Applying Agile Portfolio Operations — Official range: 12–14% (Practice allocation: 13.4%)

    • Value Stream Coordination
    • ART Execution and Operational Excellence
  • Applying Lean Governance — Official range: 8–10% (Practice allocation: 9.28%)

    • Measure Lean Portfolio Performance
    • Continuous Compliance

How to prepare

Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.

These independent practice questions are not actual exam items and do not guarantee a passing result.

Frequently asked questions

What is the exam format?

Web-based, closed book, no outside assistance; multiple-choice, single-select

How many questions are on the exam?

Total questions: 45.

How long is the exam?

90 minutes

What is the passing score?

77%

How much does the exam cost?

First attempt included in course registration fee within 60 days of completion; retake fee $50

Official sources and references

Confirm current exam arrangements with the exam provider.