Free PECB Certified PSM Basic Practice Questions
100 free questions · Answer explanations · No signup required
View examination details, outline and sourcesLoading selected examination banks…
Sample Practice Questions
Try these 10 sample questions from the PECB Certified PSM Basic practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.
1A project team is in the initial phase of the worry curve before it has examined the project's risks. Which behavior best characterizes this phase?
- A.Assuming minor issues can wait because time seems abundant.Correct answer: A
- B.Relying on a shared plan to address identified project risks.
- C.Feeling concern about progress without a clear basis for it.
- D.Taking urgent recovery steps while cost and quality suffer.
Explanation: Project Success describes the initial phase as one where "everything feels on track, and minor issues are ignored" because there seems to be time. It contrasts this with emerging concerns and eventual panic as deadlines approach.
Reference: Advantages of the Project Success Method — Shifting the Worry Curve
2A sponsor needs a document to formally authorize a new project and give its manager authority to use organizational resources for project activities. Which document serves this purpose?
- A.Project management plan
- B.Project schedule
- C.Project budget
- D.Project charterCorrect answer: D
Explanation: The PMI lexicon defines the project charter as "A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities." That is the authorization the sponsor needs.
Reference: PMI Lexicon of Project Management Terms — Version 5.0, page 21, project charter
3During project planning, a team assigns one person as the single point of contact who will ensure a particular activity is completed, although others may perform its work. Which role is being assigned?
- A.Project manager
- B.Activity managerCorrect answer: B
- C.Functional manager
- D.Resource manager
4On a facility project, equipment installation cannot start until the foundation inspection has finished. Which logical relationship directly represents this dependency?
- A.Finish-to-finish
- B.Start-to-start
- C.Finish-to-startCorrect answer: C
- D.Start-to-finish
Explanation: The PMI lexicon defines finish-to-start as "A logical relationship in which a successor activity cannot start until a predecessor activity has finished." Installation is the successor and inspection is the predecessor.
Reference: PMI Lexicon of Project Management Terms — Version 5.0, finish-to-start
5To estimate the duration of a new installation, a planner uses the actual duration of a comparable installation completed previously. Which estimating technique is the planner using?
- A.Analogous estimatingCorrect answer: A
- B.Bottom-up estimating
- C.Parametric estimating
- D.Multipoint estimating
Explanation: The PMI lexicon defines analogous estimating as "A technique for estimating the duration, cost, or required resources for an activity or project using historical data from a similar activity or project." The planner is using a similar completed activity as the basis.
Reference: PMI Lexicon of Project Management Terms — Version 5.0, page 2, analogous estimating
6Four independent paths start together and must all finish before project completion. Path A takes 3 then 4 days; path B takes 5 then 4 days; path C takes 4 then 4 days; path D takes 3 then 3 days. With no other constraints, which path is critical?
- A.Path A
- B.Path BCorrect answer: B
- C.Path C
- D.Path D
Explanation: The lexicon defines the critical path as "The sequence of activities that represents the longest path through a project, which determines the shortest possible duration." The path durations are A = 7, B = 9, C = 8, and D = 6 days, so B is longest.
Reference: PMI Lexicon of Project Management Terms — Version 5.0, critical path
7To shorten a project without changing its scope, the team overlaps two phases that were previously planned in sequence. Which compression technique is the team applying?
- A.Resource smoothing
- B.Resource leveling
- C.Fast trackingCorrect answer: C
- D.Crashing
Explanation: The PMI lexicon describes fast tracking as "A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration." The team overlaps phases that had been sequential.
Reference: PMI Lexicon of Project Management Terms — Version 5.0, fast tracking
8To analyze workforce needs, a planner assigns named categories of personnel and equipment to scheduled project activities. Which process is the planner performing?
- A.Budget loading
- B.Cost loading
- C.Resource loadingCorrect answer: C
- D.Resource leveling
Explanation: NASA defines resource loading as "The process of assigning specific resources (i.e., workforce, materials, equipment, etc.) to a schedule activity or a group of activities for the purposes of estimating Program or project duration, cost, feasibility, and workforce planning." The planner is making those activity assignments.
Reference: NASA Program Planning and Control Glossary — Resource Loading
9A project review finds that work is already deviating from the approved plan. The manager directs an action intended to realign current performance with that plan. What type of action is this?
- A.Preventive action
- B.Corrective actionCorrect answer: B
- C.Risk acceptance
- D.Risk transference
10A team uses a three-phase method: it charters the project, develops its schedule, then monitors and updates the plan. Which phase sequence corresponds to those activities?
- A.Plan, define, control
- B.Control, plan, define
- C.Define, plan, controlCorrect answer: C
- D.Define, control, plan
Topics in this practice bank
These topics describe the available practice for PECB Certified PSM Basic. Review the examination outline and its sources for scope and allocation details.
Fundamental principles and concepts of The Project Success Method
- Competencies
- Knowledge statements
Core team formation and project chartering
- Competencies
- Knowledge statements
Work breakdown structure/team organization
- Competencies
- Knowledge statements
Precedence relationships and network analysis
- Competencies
- Knowledge statements
Activity duration estimating
- Competencies
- Knowledge statements
Scheduling calculations and validation
- Competencies
- Knowledge statements
Project duration and schedule compression analysis
- Competencies
- Knowledge statements
Project staffing and budgeting
- Competencies
- Knowledge statements
Project updates and control
- Competencies
- Knowledge statements
How to use these free practice questions
Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.
These are independent study questions, not actual examination items. For examination requirements and official information, view PECB Certified PSM Basic details.