1When must an Oregon contractor hold a current CCB license and proper endorsement when bidding compensated construction work?
- A. Before submitting the bid
- B. Only after award
- C. At first payment
- D. After permit issuance
Answer: A
Explanation: The controlling source states, "must have a current license issued by the Construction Contractors Board." ORS 701.021 requires current licensure and an appropriate endorsement when a person undertakes, offers, or submits a bid for contractor work.
2Which structure is the simplest one-owner business form but leaves the owner personally liable for all obligations?
- A. Corporation
- B. General partnership
- C. Limited liability company
- D. Sole proprietorship
Answer: D
Explanation: The controlling source states, "the simplest form of business where one individual conducts the business." The Oregon Secretary of State describes a sole proprietorship as one individual conducting the business with personal liability for its obligations.
Reference: Oregon Secretary of State : Business Types : State of Oregon — Sole Proprietorships
3What should a prime contractor verify before assigning Oregon construction work to a subcontractor?
- A. A current workers' compensation policy only
- B. Required CCB license and proper endorsement
- C. A current general liability policy only
- D. An Oregon payroll identification number only
Answer: B
Explanation: The controlling source states, "must have a current license issued by the Construction Contractors Board." ORS 701.021 requires licensing to undertake contractor work, and ORS 701.131 requires proper endorsement for compensation rights.
4Above what aggregate price must an Oregon residential construction agreement generally be written?
5Under Oregon's standard invitation-to-bid method for a public improvement, to whom is award generally made?
- A. Highest-ranked responsive proposer
- B. Lowest responsive, responsible bidder
- C. Contractor selected by direct appointment
- D. Offeror selected after competitive negotiation
6Which project-management document defines how an Oregon agency will manage, document, monitor, and control contract performance?
- A. Contract Administration Plan
- B. Notice to Proceed
- C. Contract Amendment
- D. Change Order
Answer: A
Explanation: The official manual states, "The Contract Administration Plan (CAP) defines how the agency will manage the contract and document, monitor and control contract performance." That definition identifies the CAP, rather than a change instrument or authorization notice.
Reference: Das Contract Administration — Develop Contract Administration Plan
7At what height must Oregon construction employees generally be protected from unprotected sides or edges?
- A. Four feet above a lower level
- B. Ten feet above a lower level
- C. Fifteen feet above a lower level
- D. Six feet or more above a lower level
Answer: D
Explanation: The controlling source states, "6 feet or more above lower levels." Oregon OSHA's construction fall-protection rule generally requires protection at unprotected sides and edges six feet or more above a lower level.
Reference: Fall Protection — OAR 437-003-1501, unprotected sides and edges
8Before renovation or demolition, which Oregon structure generally requires an asbestos survey?
- A. A commercial structure of any age or a residential structure built before 2004
- B. Commercial structures built before 2004 and residential structures of any age
- C. Commercial and residential structures built before 1990
- D. Commercial and residential structures built during or after 2004
Answer: A
Explanation: The controlling source states, "All commercial buildings regardless of construction date and residential buildings constructed before 2004." Oregon DEQ requires an accredited asbestos survey for commercial structures regardless of age and residential structures constructed before 2004, subject to stated exceptions.
Reference: Department of Environmental Quality : Asbestos Survey Resources : Hazards and Cleanup : State of Oregon — OAR 340-248-0270(1)-(4)
9In a basic accounting system, where are business transactions first recorded chronologically?
- A. General ledger
- B. Trial balance
- C. Journal
- D. Income statement
Answer: C
Explanation: The controlling source states, "A journal is a book where you record each business transaction." IRS Publication 583 explains that journals are books of original entry in which transactions are recorded before posting to ledgers.
Reference: Publication 583 (12/2024), Starting a Business and Keeping Records | Internal Revenue Service — Recording business transactions; journals and ledgers
10What must an Oregon employer obtain before issuing any employee paycheck?
- A. Federal employer identification number
- B. Oregon CCB license number
- C. Oregon Business Registry number
- D. Oregon business identification number
Answer: D
Explanation: The controlling source states, "You must register before issuing any paychecks." Oregon Department of Revenue payroll guidance directs employers to register for a business identification number before issuing paychecks.
Reference: Dor Withholding Payroll — Registering for payroll tax; business identification number
Topics in this practice bank
These topics describe the available practice for Oregon Construction Contractors. Review the examination outline and its sources for scope and allocation details.
- Oregon Const. Contractor Laws and Regulations
- Choosing Your Business Structure
- Hiring and Managing Employees
- Working with Subcontractors
- Contracts
- Oregon Lien Law
- Bidding and Estimating
- Scheduling and Project Management
- Oregon Building Codes
- Jobsite Safety
- Environmental Factors
- Building Exterior Shell
- Financial Management
- Tax Basics
How to use these free practice questions
Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.
These are independent study questions, not actual examination items. For examination requirements and official information, view Oregon Construction Contractors details.