Free NICET Electrical Power Testing, Level II Practice Questions
200 free questions · Answer explanations · No signup required
View examination details, outline and sourcesLoading selected examination banks…
Sample Practice Questions
Try these 10 sample questions from the NICET Electrical Power Testing, Level II practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.
1Before disconnecting fixed electrical equipment for maintenance, when must its safe deenergizing procedure be determined?
- A.Before deenergizing beginsCorrect answer: A
- B.After disconnecting but before applying locks
- C.After applying locks but before voltage testing
- D.After voltage testing but before maintenance
2During commissioning of a medium-voltage disconnect in a generator cubicle, what does checking blade alignment and penetration primarily verify?
- A.Mechanical engagement and operation of the switch contactsCorrect answer: A
- B.Electrical resistance of the closed contact interface
- C.Insulation strength across the open contact gap
- D.Electrical correspondence of the auxiliary position signal
Explanation: The specified checks establish "blade alignment, blade penetration and operation". A is the mechanical engagement judgment. Contact resistance, open-gap dielectric testing, and an auxiliary-contact indication test assess B, C and D respectively; blade alignment alone does not establish those electrical results.
Reference: Bureau of Reclamation — FIST 4-7 Commissioning Guide for Hydroelectric Facilities — p. 96 / 6.1.30 Generator Neutral Cubicle / disconnect-switch tests
3A 20-hp motor has a nameplate service factor of 1.15. Under the conditions specified for that factor, what power loading does the multiplier indicate?
- A.20.15 hp
- B.17.39 hp
- C.3 hp
- D.23 hpCorrect answer: D
Explanation: The guide calls service factor a "multiplier" applied to rated power. Thus 20 × 1.15 = 23 hp. 20.15 adds unlike quantities; 17.39 divides instead of multiplying; 3 hp is only the increment. This does not recommend routine operation above rated horsepower.
Reference: U.S. Department of Energy — Premium Efficiency Motor Selection and Application Guide — Glossary, service factor
4An ideal 24-V DC source is connected across an 8-ohm resistor. What current flows?
- A.192 A
- B.0.333 A
- C.16 A
- D.3 ACorrect answer: D
Explanation: The handbook states, "Current is equal to the applied voltage divided by the circuit resistance." I = V/R = 24/8 = 3 A. 192 multiplies V by R; 0.333 reverses the division; 16 subtracts unlike quantities.
Reference: U.S. Department of Energy — DOE-HDBK-1011/1-92 Electrical Science — ES-01, p. 14, Ohm’s Law
5An electrically powered test stand has a STOP push button and a separate supply disconnect. For work requiring deenergization under OSHA, which statement about the STOP button is correct?
- A.It replaces the supply disconnect if its lamp is off
- B.It may stop operation but cannot be the sole means of deenergizationCorrect answer: B
- C.It replaces lockout when held in the stopped position
- D.It proves absence of voltage when the motor stops
Explanation: OSHA says control devices “may not be used as the sole means for deenergizing.” B separates stopping from energy isolation. A mistakes an indicator for isolation; C substitutes a control for lockout; D treats stopped motion as a voltage test.
Reference: OSHA — Selection and use of work practices — 29 CFR 1910.333(b)(2)(ii)(B)
6A medium-voltage disconnect operates correctly, but its remote position indication is reversed. Which switch check most directly addresses this discrepancy?
- A.Compare the auxiliary-contact state with the actual switch positionCorrect answer: A
- B.Measure resistance across the closed main contacts
- C.Measure insulation resistance across an open pole
- D.Inspect the blade's mechanical penetration
Explanation: The auxiliary contact must indicate the "correct position of the disconnect switch." A checks the electrical position signal directly. B assesses conduction, C insulation, and D mechanical engagement; none directly verifies the auxiliary indication.
Reference: Bureau of Reclamation — FIST 4-7 Commissioning Guide for Hydroelectric Facilities — p. 96 / 6.1.30 Generator Neutral Cubicle / disconnect-switch tests
7What does a motor's standardized frame size principally identify?
- A.Its insulation's maximum thermal class
- B.Its instantaneous starting-current waveform
- C.Physical dimensions needed for interchangeabilityCorrect answer: C
- D.Its actual operating power factor
Explanation: The source states, "frame size – A set of physical dimensions of motors as established by National Electrical Manufacturers Association for interchangeability between manufacturers." The physical frame designation supports checks of mounting and shaft dimensions. Power factor, insulation class, and starting-current characteristics are separate electrical data.
Reference: U.S. Department of Energy — Premium Efficiency Motor Selection and Application Guide — Glossary, frame size
8Three resistors of 6, 9, and 15 ohms are connected in series. What equivalent resistance does the source see?
- A.15 ohms
- B.10 ohms
- C.30 ohmsCorrect answer: C
- D.2.90 ohms
Explanation: The handbook states, "The total resistance in a series circuit is equal to the sum of all the parts of that circuit" R = 6 + 9 + 15 = 30 ohms. 2.90 applies the parallel reciprocal rule; 15 selects only the largest resistor; 10 averages the three instead of summing them.
Reference: U.S. Department of Energy — DOE-HDBK-1011/1-92 Electrical Science — ES-02, p. 23, Series Resistance
9A disconnected high-capacitance element retains electrical energy that could endanger the testing crew. Which preparation is required before treating it as safe?
- A.Open its supply disconnect and rely on the open gap
- B.Operate the control switch and rely on the stopped indication
- C.Discharge it, then short-circuit and ground itCorrect answer: C
- D.Ground only its enclosure and retain the stored charge
Explanation: OSHA requires high-capacitance elements to be “short-circuited and grounded” after hazardous stored energy is released. C performs those actions. A and B do not remove retained charge; D grounds the enclosure rather than controlling the stored energy in the element.
Reference: OSHA — Selection and use of work practices — 29 CFR 1910.333(b)(2)(ii)(C)
10Which measurement directly evaluates the conductive path across the closed blade contacts of a medium-voltage disconnect?
- A.Contact resistance across the closed bladeCorrect answer: A
- B.Insulation resistance across the open contact gap
- C.Insulation resistance from a phase to the enclosure
- D.Resistance of the position-indication control coil
Explanation: The guide calls for "contact resistance across each blade". A measures the closed current-carrying interface. B and C measure insulating paths, while D measures a control coil rather than the main-contact interface.
Reference: Bureau of Reclamation — FIST 4-7 Commissioning Guide for Hydroelectric Facilities — p. 96 / 6.1.30 Generator Neutral Cubicle / disconnect-switch tests
Exam Review
About NICET Electrical Power Testing, Level II
NICET Electrical Power Testing, Level II · US
Key exam facts
- Provider
- National Institute for Certification in Engineering Technologies (NICET): certification examination owner; Pearson VUE: computer-based test delivery/administration.
- Format
- In-person computer-based examination; most questions are multiple choice or multiple select, with some picture-based point selection. References are not permitted.
- Exam questions
- Total questions: 136.
- Time limit
- 155 minutes answering questions; an additional 10-minute introductory tutorial is outside the answering time.
- Passing score
- Minimum passing scaled score 500 on the 0–700 scale. Scores below 200 are reported as 200, and scores of 500 or above are reported as Pass; this is not a raw percentage.
- Exam fee
- US standard Level II CBT application fee: $325 (US dollars), effective August 1, 2026; no state/local taxes are added. Rescheduling outside the permitted window may incur an additional fee equal to half the original testing fee.
Topics covered
The authority publishes percentage ranges for each content area. The practice percentages below use the midpoint of each range, normalized to 100%; they are not exact percentages published by the authority. Practice question counts may differ slightly because of rounding.
Safety Procedures — Official range: 20–30% (Practice allocation: 25%)
- Apply lockout/tagout procedures.
- Apply general safety guidelines.
- Understand test equipment safety.
- Apply personal protective equipment (PPE).
General Testing — Official range: 32–42% (Practice allocation: 37%)
- Demonstrate testing knowledge for medium voltage (MV) switches.
- Demonstrate testing knowledge of cables (medium-voltage and low-voltage).
- Demonstrate testing knowledge of transformers.
- Demonstrate testing knowledge of rotating machinery.
- Demonstrate testing knowledge of switchgear and motor control centers.
- Demonstrate testing knowledge of low-voltage and medium-voltage circuit breakers.
- Demonstrate testing knowledge of relays and metering.
- Demonstrate testing knowledge of surge protection, capacitors, reactors, arrestors.
- Demonstrate testing knowledge of grounding systems.
- Demonstrate testing knowledge of battery systems.
- Compare test results to standard or like equipment.
Documentation and Standards — Official range: 13–23% (Practice allocation: 18%)
- Recognize nameplate data.
- Record test data.
- Identify the most common IEEE/ANSI electrical device function numbers.
- Recognize the scope of standards and regulatory organizations.
Electrical Theory and Troubleshooting — Official range: 15–25% (Practice allocation: 20%)
- Apply fundamental electrical laws to simple circuits.
- Troubleshoot basic electrical problems.
How to prepare
Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.
These independent practice questions are not actual exam items and do not guarantee a passing result.
Frequently asked questions
What is the exam format?
In-person computer-based examination; most questions are multiple choice or multiple select, with some picture-based point selection. References are not permitted.
How many questions are on the exam?
Total questions: 136.
How long is the exam?
155 minutes answering questions; an additional 10-minute introductory tutorial is outside the answering time.
What is the passing score?
Minimum passing scaled score 500 on the 0–700 scale. Scores below 200 are reported as 200, and scores of 500 or above are reported as Pass; this is not a raw percentage.
How much does the exam cost?
US standard Level II CBT application fee: $325 (US dollars), effective August 1, 2026; no state/local taxes are added. Rescheduling outside the permitted window may incur an additional fee equal to half the original testing fee.
Official sources and references
- NICET Electrical Power Testing Level II Content Outline
p. 1 / release heading
- NICET Electrical Power Testing Level II Selected General References
p. 1 / title and use restrictions
- NICET Exams
Scaled Score
- NICET Exams
Number of Questions and Time Allowed
- NICET Electrical Power Testing
What to Expect / Level II Exam
- NICET Electrical Power Testing
Pricing / Standard Model/CBT Application / Level II
- NICET Electrical Power Testing
Test Time
- NICET Electrical Power Testing
What is the Test Like?
Confirm current exam arrangements with the exam provider.