1What was the origin of the Toyota Production System's jidoka concept?
- A.A system that replenishes parts after they are withdrawn
- B.A loom that incorporated the ability to make judgmentsCorrect answer: B
- C.A line that moved work through fixed assembly stations
- D.A process for scheduling mixed batches of vehicles
2In lean management, what does an organization's True North express?
- A.A temporary plan for a single improvement project
- B.A record of current performance against this month's target
- C.Its strategic and philosophical vision or purposeCorrect answer: C
- D.A detailed work instruction for a specific task
3A team is defining a problem about late customer orders. Which statement describes the gap in a measurable way?
- A.The current on-time delivery rate is 82%, compared with the customer requirement of 95%.Correct answer: A
- B.Customers would be happier if the delivery process were improved in some way.
- C.The team should immediately install a new scheduling system for every order.
- D.The shipping department needs to perform much better than it did previously.
Explanation: The Lean Enterprise Institute describes a good problem statement as the "difference between our target condition and our actual condition stated in observable and measureable terms". The rate and requirement make that difference explicit.
Reference: Why Effective Problem Solving Begins With a Good Problem Statement — Problem Solving, problem statement definition
5In a visual workplace, which comparison helps a team recognize an abnormal process condition?
- A.One future improvement target against another target
- B.Actual performance against the defined process standardCorrect answer: B
- C.Two unverified explanations for the same process problem
- D.Past process observations without a defined normal standard
6In a SIPOC diagram, which element identifies who provides materials or information to the process?
7How does a special cause of variation differ from a common cause?
- A.It can be intermittent and affect only some process outputs.Correct answer: A
- B.It is inherent in every output of the process.
- C.It is always identical to ordinary process variation.
- D.It must affect every observation by the same amount.
8According to Toyota, what is the intended relationship between waste elimination and lead time in its production system?
- A.Reduce lead time by delaying waste elimination
- B.Reduce waste while allowing lead time to grow
- C.Reduce both waste and process lead timeCorrect answer: C
- D.Focus on output volume without reducing waste
9Which combination illustrates the kinds of elements that True North may bring together?
- A.A profit objective and a broader organizational purposeCorrect answer: A
- B.A past profit figure and the same period's revenue figure
- C.A workstation's cycle time and its daily production count
- D.A task instruction and the schedule for checking it
10Which statement describes a customer-service problem rather than prescribing a solution?
- A.Install an automated reminder system for overdue requests.
- B.Assign another person to answer every overdue request.
- C.Service requests exceed the two-day response target in 18% of cases.Correct answer: C
- D.Replace the current request-tracking software with a new platform.
Topics in this practice bank
These topics describe the available practice for EXIN LSSA Lean Six Sigma Yellow Belt. Review the examination outline and its sources for scope and allocation details.
World-class performance
- Continuous improvement
- Customer value
Policy development and deployment
- Policy development
- Policy deployment
Project management
- Managing a project
- Process improvement roadmaps
Creating a solid foundation
- Professional work environment
- Standardized work
- Quality management
Creating a continuous improvement culture
- Visual management
- Performance management
- Basic quality tools
Creating stable and efficient processes
- Process mapping
- Performance metrics
- Basic statistics
- Value stream analysis
- Reducing Muda (Waste)
- Reducing Muri (Overburden)
- Reducing Mura (Unevenness)
- Process and quality control
Creating capable processes
- Statistical techniques
- Distributions
- Measurement systems
- Hypothesis testing and confidence intervals
- Tests for means, variances and proportions
- Correlation and regression
How to use these free practice questions
Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.
These are independent study questions, not actual examination items. For examination requirements and official information, view EXIN LSSA Lean Six Sigma Yellow Belt details.