  1. 1A telecommunications contract governed by the FAR is firm-fixed-price. The agreed scope remains unchanged, but the contractor underestimated installation labor. Which statement describes the contractor's cost exposure?

    1. A. The owner reimburses the overrun because the scope is unchanged.
    2. B. The contractor bears the overrun under the agreed fixed price.
    3. C. The parties automatically split the overrun in equal shares.
    4. D. The price converts to actual cost plus the original profit.

    Answer: B

    Explanation: FAR 16.202-1 states, "This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss." With no scope change or other adjustment basis, underestimated labor remains the contractor’s cost risk; reimbursement, automatic sharing, and automatic conversion do not follow.

    Reference: Federal Acquisition Regulation, Part 16 — Types of Contracts — 16.202-1

  2. 2A value-engineering review compares two cabling designs that meet the same required capacity, reliability, and safety criteria. What is the appropriate cost objective?

    1. A. Reduce initial cost even if required capacity is lost.
    2. B. Choose the option with the greatest number of features.
    3. C. Reduce acquisition, operation, or support cost while preserving essentials.
    4. D. Choose the option with the lowest purchase price regardless of maintenance.

    Answer: C

    Explanation: FAR 48.101(a) states, "Value engineering attempts to eliminate, without impairing essential functions or characteristics, anything that increases acquisition, operation, or support costs." The review must preserve essential requirements while removing unnecessary cost. Feature count and initial price alone do not establish value.

    Reference: Federal Acquisition Regulation — Value Engineering — 48.101(a)

  3. 3A federal telecommunications service is being specified through a performance work statement under FAR 37.602. Which emphasis follows that approach?

    1. A. The required service results rather than a prescribed number of labor hours
    2. B. The contractor's staffing method rather than the required service results
    3. C. The owner's preferred work sequence rather than the required service results
    4. D. The amount of contractor effort regardless of the delivered service results

    Answer: A

    Explanation: FAR 37.602(b)(1) directs agencies, to the maximum extent practicable, to "Describe the work in terms of the required results". A performance work statement emphasizes outcomes rather than specifying effort or method as the substitute for those outcomes.

    Reference: Federal Acquisition Regulation — Performance Work Statement — 37.602(b)(1)

  4. 4Which structure breaks the telecommunications project's required products and work into progressively smaller elements for planning and control?

    1. A. A stakeholder contact directory
    2. B. A project organization chart
    3. C. A work breakdown structure
    4. D. A chronological meeting calendar

    Answer: C

    Explanation: GAO explains, "Elements such as hardware, software, and data are further broken down into specific lower-level elements." This hierarchical decomposition is the WBS. A contact directory identifies people, an organization chart shows authority, and a meeting calendar lists events rather than decomposing project scope.

    Reference: GAO Cost Estimating and Assessment Guide — Chapter 7, WBS Concepts, p. 56

  5. 5A telecommunications construction contract adopts UFGS 01 30 00 paragraph 1.8. What is the main purpose of its preconstruction conference?

    1. A. Use the conference for design alternatives while each trade sets its own administrative procedures.
    2. B. Develop shared understanding of reporting, invoicing, safety, access, outage, and scheduling requirements.
    3. C. Limit the conference to the contract price while administrative implementation is handled separately by each team.
    4. D. Present the contract administratively without discussing how its project requirements will be implemented.

    Answer: B

    Explanation: UFGS 01 30 00 identifies the purpose as "discuss and develop a mutual understanding of the administrative requirements of the Contract". Its agenda includes reporting, invoicing, safety, access, outages, and scheduling. A design-only or price-only discussion, or a presentation without implementation discussion, does not establish that shared administrative understanding.

    Reference: UFGS 01 30 00 — Administrative Requirements — 1.8 Preconstruction Meeting Conference, p. 8

  6. 6A NAVFAC Pacific telecommunications project adopts the mobilization definition in UFGS 01 30 00 paragraph 1.16. Which condition constitutes mobilization under that definition?

    1. A. Equipment is scheduled for delivery, but no project personnel are on site.
    2. B. A project manager attends an off-site meeting while equipment remains at the yard.
    3. C. A worker visits the site, but no contractor equipment is present there.
    4. D. Equipment and at least one member of the contractor's team are on the jobsite.

    Answer: D

    Explanation: UFGS 01 30 00 defines mobilization as "having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite." Both elements must be present. A delivery plan, an off-site meeting, or personnel without equipment omits a required element.

    Reference: UFGS 01 30 00 — Administrative Requirements — 1.16 Mobilization, p. 14

  7. 7A stakeholder report lists significant schedule and cost variances. Which addition explains why performance differs from the plan and how the team is responding?

    1. A. Additional baseline and expenditure tables without explaining the origins of the variances
    2. B. Next-period performance targets substituted for the current variance assessment
    3. C. Causes of significant variances, emerging trends, and the related corrective plans
    4. D. A list of proposed actions without relating them to variance causes or performance trends

    Answer: C

    Explanation: GAO describes communicating "what is causing significant variances and developing trends and what corrective action plans are in place". This explains both the performance difference and the response. Extra figures or future targets do not explain the causes; actions unconnected to causes and trends do not answer why the variance arose.

    Reference: GAO Cost Estimating and Assessment Guide — Chapter 19, Analyze Performance, p. 250

  8. 8A government inspector witnesses a successful test on a federal telecommunications construction project governed by FAR 52.246-12. Does the inspection or test by itself constitute acceptance?

    1. A. Yes, every government-witnessed test constitutes final acceptance.
    2. B. Yes, provided the contractor has submitted a progress invoice.
    3. C. Yes, if the inspector's attendance is entered in the official daily report.
    4. D. No, government inspection and testing do not themselves imply acceptance.

    Answer: D

    Explanation: FAR 52.246-12(c) provides that government inspections and tests do not "Constitute or imply acceptance". A successful witnessed test, a progress invoice, or a daily record of inspector attendance does not by itself establish formal acceptance.

    Reference: Federal Acquisition Regulation — Inspection of Construction — 52.246-12(c)(3)

  9. 9How does a FAR time-and-materials contract normally establish payment for installation labor and materials?

    1. A. A fixed total price for labor and estimated prices for materials
    2. B. Actual labor costs plus a fee and fixed prices for materials
    3. C. Fixed unit prices for completed outlets and no materials charge
    4. D. Specified fixed hourly labor rates and actual material costs

    Answer: D

    Explanation: FAR 16.601(b) specifies "Direct labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses, and profit" and "Actual cost for materials". This payment structure differs from lump-sum, cost-plus labor, and unit-price output arrangements.

    Reference: Federal Acquisition Regulation, Part 16 — Types of Contracts — 16.601(b)(1)–(2)

  10. 10Two telecommunications systems have the same purchase and installation price. One has higher expected annual maintenance and replacement costs. What does life-cycle cost analysis add to the comparison?

    1. A. It includes costs incurred over the operating life.
    2. B. It compares the purchase prices without future costs.
    3. C. It treats every maintenance cost as a sunk cost.
    4. D. It replaces operating costs with equipment list prices.

    Answer: A

    Explanation: DOE explains that life-cycle cost categories "may include the purchase cost, construction cost, fuel cost, operation cost, maintenance cost, replacement cost, disposal cost, and fees associated with loans." Thus equal initial prices do not imply equal life-cycle costs. Future maintenance and replacement must remain in the comparison.

    Reference: DOE Building Science Education — Life-Cycle Analysis — Life-Cycle Analysis, cost-analysis paragraph

Topics in this practice bank

These topics describe the available practice for BICSI Registered Telecommunications Project Manager (RTPM) Exam. Review the examination outline and its sources for scope and allocation details.

  • Obtain and Review Specific Project Information
  • Create Initial Project Budget Estimation
  • Develop Project Proposal
  • Create and Assemble Project Deliverables
  • Perform Project Administrative Activities
  • Manage Project Implementation
  • Communicate Project Status to Stakeholders (Communication Plan)
  • Conduct Project Closure

How to use these free practice questions

Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.

These are independent study questions, not actual examination items. For examination requirements and official information, view BICSI Registered Telecommunications Project Manager (RTPM) Exam details.