Free BCS Foundation Certificate in IS Project Management Practice Questions
100 free questions · Answer explanations · No signup required
View examination details, outline and sourcesLoading selected examination banks…
Sample Practice Questions
Try these 10 sample questions from the BCS Foundation Certificate in IS Project Management practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.
1An organization forms a temporary team to deliver a new custom information system and disbands it when delivery is complete. What is this undertaking?
- A.A projectCorrect answer: A
- B.A program
- C.A portfolio
- D.An operation
2An IT project produces a tested data-conversion design that the team needs to build the final system. How is that design best classified in relation to the final deliverable?
- A.An interim deliverableCorrect answer: A
- B.A project milestone
- C.A final deliverable
- D.A project dependency
3A project team updates its schedule using work completed through a specified reporting date. What is that date called in scheduling terminology?
- A.The baseline date
- B.The data dateCorrect answer: B
- C.The milestone date
- D.The target date
4An IT project needs to identify controlled system components, track their versions, and manage changes to them. Which management discipline addresses this need?
- A.Configuration managementCorrect answer: A
- B.Change control
- C.Requirements management
- D.Quality management
Explanation: NASA describes configuration management as “identifying and defining the configuration items in a system, controlling the release and change of these items throughout the system life cycle”. That directly addresses controlled components and their changes.
Reference: NASA Software Engineering Handbook: Software Configuration Management Plan — Section 2, Rationale
5An IT project reviews whether its development processes are designed and managed to prevent defects. Which quality activity does this primarily illustrate?
- A.Quality control
- B.Quality assuranceCorrect answer: B
- C.Acceptance testing
- D.Integration testing
Explanation: ISO describes quality assurance as “process-oriented and preventive” and explains that it focuses on managing work to prevent defects. That is the emphasis of this review.
Reference: Quality Assurance: A Critical Ingredient for Organizational Success — What is the difference between quality assurance and quality control?
6Three analysts will each work full time for four working days on a task, with no idle time. What is the estimated effort for the task?
- A.3 staff-days
- B.4 staff-days
- C.7 staff-days
- D.12 staff-daysCorrect answer: D
7A project team identifies that a supplier might miss a future delivery date, which would delay deployment. The delivery date has not yet arrived. How should this possible event be classified?
- A.An issue
- B.A riskCorrect answer: B
- C.A milestone
- D.An assumption
Explanation: NASA defines risk using “the likelihood (i.e., probability of occurrence) and the consequence(s) (i.e., impact) of a future undesired event or scenario”. The supplier delay is a possible future event with an adverse project consequence.
Reference: NASA Project Planning and Control Glossary — Risk
8An organization coordinates several related IT projects together to obtain benefits unavailable if they were managed separately. In PMI terminology, what is this grouping called?
- A.A programCorrect answer: A
- B.A project portfolio
- C.A project management office
- D.A project steering committee
Explanation: PMI defines a program as “A group of related projects and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.” The coordinated projects fit this description.
Reference: PMI Lexicon of Project Management Terms — Program, p. 20
9Before an information-system project starts, the manager creates a schedule for its deliverables. What planning purpose does the schedule serve?
- A.It shows why the deliverables justify the investment
- B.It shows how and when the deliverables will be producedCorrect answer: B
- C.It shows whether the deliverables meet quality criteria
- D.It shows which deliverables need changes to requirements
Explanation: The scheduling standard says that “Scheduling provides a detailed plan that represents how and when the project will deliver the products, services, and results defined in the project scope”. The schedule provides this delivery plan.
Reference: Practice Standard for Scheduling, Second Edition — Section 1.2, Why Scheduling?, p. 1
10A project team must produce and verify a requirements specification before completing a development phase. What project planning term describes that specification?
- A.A dependency
- B.A milestone
- C.A deliverableCorrect answer: C
- D.An activity
Explanation: PMI defines a deliverable as “Any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project.” The required specification is a verifiable product of the phase.
Reference: Practice Standard for Scheduling, Second Edition — Glossary, Deliverable
Exam Review
About BCS Foundation Certificate in IS Project Management
BCS Foundation Certificate in IS Project Management · US
Key exam facts
- Provider
- Pearson VUE; BCS accredited training-provider route also available
- Format
- Supervised online multiple-choice examination; closed book; calculators prohibited.
- Exam questions
- Total questions: 40.
- Time limit
- 60 minutes; 15 additional minutes (25%) when the examination language is not the candidate's native/official language; reasonable adjustments by application.
- Passing score
- 65% (26/40)
Topics covered
Projects and Project Work (15%)
- Definition of a project
- Purpose of project planning and control
- System development life cycle
- Project Management and the Development Life cycle
- Development life cycles
- Agile project practices
- Types of project plans
- Purpose and content of a business case
- Transition strategies
- Post implementation review
Project Planning (15%)
- Project deliverables and intermediate products
- Work and product breakdown structures
- Product definitions
- Activity planning
- Resource allocation, smoothing and levelling, resource histograms
- Gantt charts
Monitoring and Control (10%)
- Project control life cycle
- Monitoring progress
- Purpose and types of progress reporting
- Corrective action
- Presenting progress information
Change Control and Configuration Management (5%)
- Reasons for change control and configuration management
- Change control procedures
- Configuration management
Quality (12.5%)
- Definitions of the term ‘quality’
- Quality characteristics
- Quality control versus quality assurance
- Detecting defects during the project life cycle
- Quality process requirements
- Defect removal processes
- Types of testing
- Principles of IS0 9001:2015
Estimating (12.5%)
- Effects of over and under-estimating
- Effort versus duration
- Estimates and targets
- Use of expert judgement
- Delphi approach
- Bottom-up estimating
- Top-down estimating
- Estimating by analogy
Risk (15%)
- Definition of the term ‘risk’
- Business and project risks
- Risk management cycle
- Identifying and prioritising risks
- Assessing risks
- Risk responses and actions
- Planning, monitoring and controlling risks
Project Communications and Project Organisation (15%)
- Relationship between programmes and projects
- Identifying stakeholders and their concerns
- Role of the project sponsor
- The project board/steering committee
- Roles and responsibilities of the project manager and project team leader/manager
- Desirable characteristics of a project manager
- Project support and management offices
- The project team and matrix management
- Team building – Tuckman-Jensen model
- Team dynamics
- Management styles
- Communication methods
How to prepare
Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.
These independent practice questions are not actual exam items and do not guarantee a passing result.
Frequently asked questions
What is the exam format?
Supervised online multiple-choice examination; closed book; calculators prohibited.
How many questions are on the exam?
Total questions: 40.
How long is the exam?
60 minutes; 15 additional minutes (25%) when the examination language is not the candidate's native/official language; reasonable adjustments by application.
What is the passing score?
65% (26/40)
Official sources and references
- BCS adoption of latest syllabus
What will I learn?, latest syllabus link
- BCS latest syllabus version
p.1, cover and version block
- BCS V9 domain 1 allocation
p.5, section 1 heading
- BCS V9 domain 2 allocation and constraint
p.5, section 2 heading and Note
- BCS V9 domain 3 allocation
p.6, section 3 heading
- BCS V9 domain 4 allocation
p.6, section 4 heading
- BCS V9 domain 5 allocation
p.6, section 5 heading
- BCS V9 domain 6 allocation
p.7, section 6 heading
- BCS V9 domain 7 allocation
p.7, section 7 heading
- BCS V9 domain 8 allocation
p.7, section 8 heading
- BCS V9 knowledge level legend
p.8, Levels of Knowledge / SFIA Levels table, K2 row (visually checked)
- BCS current examination assessment
What format is the exam?
- BCS V9 examination format table
p.8, Format of the Examination, Type row (visually checked)
- BCS V9 examination restrictions
p.8, Format of the Examination, Calculators and Delivery rows (visually checked)
- BCS self-study examination booking
Exam only (self study), preparation and delivery
- BCS V9 entry requirements
p.8, Format of the Examination, Pre-Requisite row (visually checked)
- BCS Pearson account and delivery options
How do I book my exam?
- Pearson OnVUE technical requirements
Technology Requirements, Minimum Requirements and Before Exam Day
- Pearson OnVUE identity rule
Proof of Identification Requirements, Accepted IDs
- BCS V9 language accommodation
p.4, Additional time for candidates whose language is not the language of the exam
Confirm current exam arrangements with the exam provider.