Free BCS Foundation Certificate in IS Project Management Practice Questions

100 free questions · Answer explanations · No signup required

View examination details, outline and sources

Loading selected examination banks…

Sample Practice Questions

Try these 10 sample questions from the BCS Foundation Certificate in IS Project Management practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.

  1. 1An organization forms a temporary team to deliver a new custom information system and disbands it when delivery is complete. What is this undertaking?

    1. A.A projectCorrect answer: A
    2. B.A program
    3. C.A portfolio
    4. D.An operation

    Explanation: PMI defines a project as "A temporary endeavor undertaken to create a unique product, service, or result." The bounded team is creating a unique system, so its undertaking is a project.

    Reference: Practice Standard for Scheduling, Second Edition — Glossary, Project, p. 124

  2. 2An IT project produces a tested data-conversion design that the team needs to build the final system. How is that design best classified in relation to the final deliverable?

    1. A.An interim deliverableCorrect answer: A
    2. B.A project milestone
    3. C.A final deliverable
    4. D.A project dependency

    Explanation: PMI explains that “A project might require multiple interim deliverables so that the project deliverable or final deliverable can be created or produced.” The design is an output used to create the final system.

    Reference: Project Management Skills for Life — What Is a Project?, p. 7

  3. 3A project team updates its schedule using work completed through a specified reporting date. What is that date called in scheduling terminology?

    1. A.The baseline date
    2. B.The data dateCorrect answer: B
    3. C.The milestone date
    4. D.The target date

    Explanation: PMI defines the data date as “The date through which the project status and progress were last determined and reported for analyses”. The team's reporting cutoff is its data date.

    Reference: Practice Standard for Scheduling, Second Edition — Glossary, Data Date

  4. 4An IT project needs to identify controlled system components, track their versions, and manage changes to them. Which management discipline addresses this need?

    1. A.Configuration managementCorrect answer: A
    2. B.Change control
    3. C.Requirements management
    4. D.Quality management

    Explanation: NASA describes configuration management as “identifying and defining the configuration items in a system, controlling the release and change of these items throughout the system life cycle”. That directly addresses controlled components and their changes.

    Reference: NASA Software Engineering Handbook: Software Configuration Management Plan — Section 2, Rationale

  5. 5An IT project reviews whether its development processes are designed and managed to prevent defects. Which quality activity does this primarily illustrate?

    1. A.Quality control
    2. B.Quality assuranceCorrect answer: B
    3. C.Acceptance testing
    4. D.Integration testing

    Explanation: ISO describes quality assurance as “process-oriented and preventive” and explains that it focuses on managing work to prevent defects. That is the emphasis of this review.

    Reference: Quality Assurance: A Critical Ingredient for Organizational Success — What is the difference between quality assurance and quality control?

  6. 6Three analysts will each work full time for four working days on a task, with no idle time. What is the estimated effort for the task?

    1. A.3 staff-days
    2. B.4 staff-days
    3. C.7 staff-days
    4. D.12 staff-daysCorrect answer: D

    Explanation: NASA defines effort as “The amount of work, or the number of work-time units used to complete an activity.” Three analysts working four days each contribute 3 × 4 = 12 staff-days.

    Reference: NASA Project Planning and Control Glossary — Effort

  7. 7A project team identifies that a supplier might miss a future delivery date, which would delay deployment. The delivery date has not yet arrived. How should this possible event be classified?

    1. A.An issue
    2. B.A riskCorrect answer: B
    3. C.A milestone
    4. D.An assumption

    Explanation: NASA defines risk using “the likelihood (i.e., probability of occurrence) and the consequence(s) (i.e., impact) of a future undesired event or scenario”. The supplier delay is a possible future event with an adverse project consequence.

    Reference: NASA Project Planning and Control Glossary — Risk

  8. 8An organization coordinates several related IT projects together to obtain benefits unavailable if they were managed separately. In PMI terminology, what is this grouping called?

    1. A.A programCorrect answer: A
    2. B.A project portfolio
    3. C.A project management office
    4. D.A project steering committee

    Explanation: PMI defines a program as “A group of related projects and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.” The coordinated projects fit this description.

    Reference: PMI Lexicon of Project Management Terms — Program, p. 20

  9. 9Before an information-system project starts, the manager creates a schedule for its deliverables. What planning purpose does the schedule serve?

    1. A.It shows why the deliverables justify the investment
    2. B.It shows how and when the deliverables will be producedCorrect answer: B
    3. C.It shows whether the deliverables meet quality criteria
    4. D.It shows which deliverables need changes to requirements

    Explanation: The scheduling standard says that “Scheduling provides a detailed plan that represents how and when the project will deliver the products, services, and results defined in the project scope”. The schedule provides this delivery plan.

    Reference: Practice Standard for Scheduling, Second Edition — Section 1.2, Why Scheduling?, p. 1

  10. 10A project team must produce and verify a requirements specification before completing a development phase. What project planning term describes that specification?

    1. A.A dependency
    2. B.A milestone
    3. C.A deliverableCorrect answer: C
    4. D.An activity

    Explanation: PMI defines a deliverable as “Any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project.” The required specification is a verifiable product of the phase.

    Reference: Practice Standard for Scheduling, Second Edition — Glossary, Deliverable

Exam Review

About BCS Foundation Certificate in IS Project Management

BCS Foundation Certificate in IS Project Management · US

Key exam facts

Provider
Pearson VUE; BCS accredited training-provider route also available
Format
Supervised online multiple-choice examination; closed book; calculators prohibited.
Exam questions
Total questions: 40.
Time limit
60 minutes; 15 additional minutes (25%) when the examination language is not the candidate's native/official language; reasonable adjustments by application.
Passing score
65% (26/40)

Topics covered

  • Projects and Project Work (15%)

    • Definition of a project
    • Purpose of project planning and control
    • System development life cycle
    • Project Management and the Development Life cycle
    • Development life cycles
    • Agile project practices
    • Types of project plans
    • Purpose and content of a business case
    • Transition strategies
    • Post implementation review
  • Project Planning (15%)

    • Project deliverables and intermediate products
    • Work and product breakdown structures
    • Product definitions
    • Activity planning
    • Resource allocation, smoothing and levelling, resource histograms
    • Gantt charts
  • Monitoring and Control (10%)

    • Project control life cycle
    • Monitoring progress
    • Purpose and types of progress reporting
    • Corrective action
    • Presenting progress information
  • Change Control and Configuration Management (5%)

    • Reasons for change control and configuration management
    • Change control procedures
    • Configuration management
  • Quality (12.5%)

    • Definitions of the term ‘quality’
    • Quality characteristics
    • Quality control versus quality assurance
    • Detecting defects during the project life cycle
    • Quality process requirements
    • Defect removal processes
    • Types of testing
    • Principles of IS0 9001:2015
  • Estimating (12.5%)

    • Effects of over and under-estimating
    • Effort versus duration
    • Estimates and targets
    • Use of expert judgement
    • Delphi approach
    • Bottom-up estimating
    • Top-down estimating
    • Estimating by analogy
  • Risk (15%)

    • Definition of the term ‘risk’
    • Business and project risks
    • Risk management cycle
    • Identifying and prioritising risks
    • Assessing risks
    • Risk responses and actions
    • Planning, monitoring and controlling risks
  • Project Communications and Project Organisation (15%)

    • Relationship between programmes and projects
    • Identifying stakeholders and their concerns
    • Role of the project sponsor
    • The project board/steering committee
    • Roles and responsibilities of the project manager and project team leader/manager
    • Desirable characteristics of a project manager
    • Project support and management offices
    • The project team and matrix management
    • Team building – Tuckman-Jensen model
    • Team dynamics
    • Management styles
    • Communication methods

How to prepare

Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.

These independent practice questions are not actual exam items and do not guarantee a passing result.

Frequently asked questions

What is the exam format?

Supervised online multiple-choice examination; closed book; calculators prohibited.

How many questions are on the exam?

Total questions: 40.

How long is the exam?

60 minutes; 15 additional minutes (25%) when the examination language is not the candidate's native/official language; reasonable adjustments by application.

What is the passing score?

65% (26/40)

Official sources and references

Confirm current exam arrangements with the exam provider.