Free Autodesk Certified Professional in Revit for Structural Design Practice Questions
100 free questions · Answer explanations · No signup required
View examination details, outline and sourcesLoading selected examination banks…
Sample Practice Questions
Try these 10 sample questions from the Autodesk Certified Professional in Revit for Structural Design practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.
1In a plan view, how can isolated footings be placed beneath specific selected structural columns in a single operation?
- A.Use At Grids and select the grids.
- B.Use At Columns and select the columns.Correct answer: B
- C.Use At Columns and select the grids.
- D.Use At Grids and select the columns.
Explanation: Autodesk states: "To place multiple instances of the footing beneath specific columns, click Modify | Place Isolated Foundation Multiple panel (At Columns). Select the columns and click (Finish)." At Grids instead places footings at intersections of selected grids.
Reference: Create an Isolated Foundation — Create an Isolated Foundation, multiple placement
2A nested loadable family is not shared. How are its components treated for tagging and scheduling in the host?
- A.Neither can be done separately.Correct answer: A
- B.Both can be done separately.
- C.Only tagging can be done separately.
- D.Only scheduling can be done separately.
3A legend contains symbols for two different structural component types and is placed on three sheets. How does this affect the model component instance counts in a schedule?
- A.The legend adds no model instances.Correct answer: A
- B.The legend adds one model instance in total.
- C.The legend adds one model instance per sheet.
- D.The legend adds one model instance per component type.
4A view is duplicated using Duplicate with Detailing. How are existing annotations handled and how are later annotation additions related to the original?
- A.Existing annotations are copied; later additions are independent.Correct answer: A
- B.Existing annotations are copied; later additions stay linked.
- C.Existing annotations are omitted; later additions are independent.
- D.Existing annotations are omitted; later additions stay linked.
5A linked model source has changed while the host project remains open. Which action updates the linked model without closing the host project?
- A.Reload the link.Correct answer: A
- B.Unload the link.
- C.Remove the link.
- D.Unload the link for the current user.
6A beam system must maintain the specified gap between beam exterior faces when a beam size changes. Which layout rule should be used?
- A.Fixed Distance
- B.Maximum Spacing
- C.Clear SpacingCorrect answer: C
- D.Fixed Number
Explanation: Autodesk states: "Clear Spacing is similar to the Fixed Distance value, but measures spacing between the exteriors of the beams instead of between their centerlines." It also states that adjacent beams move to maintain that distance when a beam size changes.
Reference: Modify the Layout of a Beam System — Layout Rule, Clear Spacing
7When a family is loaded using a type catalog, how are family types chosen?
- A.The user can select the types needed.Correct answer: A
- B.Every catalog type must be loaded.
- C.Only the first catalog type can be loaded.
- D.Only types already in the project can be loaded.
Explanation: Autodesk says: "A type catalog lists all of the types in a family, allowing you to select and load only the types you need for the current project, resulting in a smaller project file size." Loading types and placing instances are separate actions.
Reference: Create a Type Catalog — Create a Type Catalog, introduction
8A legend view already appears on one sheet and is added to a second sheet. Which outcome does Revit support?
- A.It must first be removed from the first sheet.
- B.It can appear on both sheets as the same legend view.Correct answer: B
- C.It must first be duplicated into a separate legend view.
- D.It is moved to the second sheet and removed from the first.
9Which view duplication workflow keeps the new view linked to the original so changes are reflected in both?
- A.Duplicate as Dependent.Correct answer: A
- B.Duplicate with Detailing as an independent view.
- C.Duplicate without detailing as an independent view.
- D.Duplicate as Dependent, then make it independent.
10What is the effect of unloading a linked model through Manage Links?
- A.It temporarily removes the linked model and allows reloading.Correct answer: A
- B.It removes the link definition from the project.
- C.It converts the link into imported model geometry.
- D.It changes the saved path while keeping the model loaded.
Exam Review
About Autodesk Certified Professional in Revit for Structural Design
Autodesk Certified Professional in Revit for Structural Design · US
Key exam facts
- Provider
- Pearson VUE
- Format
- English selected-response examination without software access; testing-center or online OnVUE delivery.
- Exam questions
- Total questions: 45–60.
- Time limit
- 120 minutes
- Passing score
- Pass/fail; numerical passing threshold is not disclosed in advance.
- Exam fee
- US$200 standard retail price
Topics covered
Modeling and materials (20%)
- Create and modify structural elements
- Use and modify element materials
- Use selection sets
Families (18%)
- Manage family categories and types
- Use family parameters
- Create family content
Documentation (22%)
- Annotate views
- Create and use detail components
- Demonstrate an understanding of phases and design options
- Use document revisions
- Configure export and print settings
Views (18%)
- Apply advanced view techniques
- Manage, create, and modify schedules
Revit project management (22%)
- Link or import files
- Define worksharing concepts
- Use levels and grids
- Transfer project standards and establish shared coordinates
- Edit object styles
- Conduct maintenance on a Revit project
- Understand shared, project, and global parameters
How to prepare
Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.
These independent practice questions are not actual exam items and do not guarantee a passing result.
Frequently asked questions
What is the exam format?
English selected-response examination without software access; testing-center or online OnVUE delivery.
How many questions are on the exam?
Total questions: 45–60.
How long is the exam?
120 minutes
What is the passing score?
Pass/fail; numerical passing threshold is not disclosed in advance.
How much does the exam cost?
US$200 standard retail price
Official sources and references
- Autodesk Revit Structural Design Exam objectives
Page 2, Exam outline, domain weighting table; complete objectives continue through page 6
- Autodesk certification details
Required skill sets, View exam objectives link
- Autodesk Exam details
Exam details, alignment to exam objectives
- Autodesk Revit Structural Design Exam objectives
Page 2, Exam format
- Autodesk certification details
Certification FAQs, How is my exam scored?
- Autodesk certification details
Certification Details
- Autodesk certification details
Certification FAQs, exam format and types of questions
- Autodesk certification details
Testing options, Trusted process and Register with your Autodesk Account
- Autodesk Certification Candidate Agreement
Page 1, Candidate Code of Conduct
- Pearson VUE Autodesk OnVUE requirements
Online testing requirements, Technology Requirements and Before Exam Day
- Pearson VUE Autodesk OnVUE requirements
Proof of Identification Requirements and Candidates Under 18
- Pearson VUE Autodesk OnVUE requirements
Testing Space Requirements, Room Requirements
- Minimum Age Requirements for Autodesk Websites, Products and Services
Page 1, minimum age rule, complete Country / Minimum Age table and service-specific qualification
Confirm current exam arrangements with the exam provider.