  1. 1What makes a situation a risk in a project?

    1. A.Its potential to affect a specific objectiveCorrect answer: A
    2. B.Its inclusion in an approved work package
    3. C.Its occurrence before the project starts
    4. D.Its allocation to the project sponsor

    Explanation: APM states: "The potential of a situation or event to impact on the achievement of specific objectives." A risk is defined through its potential effect on objectives. Work-package approval, timing before start and sponsor allocation do not define risk.

    Reference: APM Project Management Glossary — Risk

  2. 2Which outcome is a soft benefit of proactive risk management?

    1. A.A team that feels less stressed and more confidentCorrect answer: A
    2. B.A reduction in the contingency allowed in a bid
    3. C.A more competitive price for a project proposal
    4. D.A contract type that better fits the project risks

    Explanation: APM states: "the project team is less stressed, more confident and is better able to apply its skills." Reduced stress and greater confidence are soft human benefits. Contingency, bid price and contract fit are commercial or planning benefits.

    Reference: Project Risk Analysis and Management Guide – publisher sample — p. 2, Approaches to risk management in projects

  3. 3Which event is a threat to a project objective?

    1. A.A possible supplier delay that would postpone completionCorrect answer: A
    2. B.An approved deliverable that meets acceptance criteria
    3. C.A confirmed saving already included in the final accounts
    4. D.A planned meeting used to discuss possible responses

    Explanation: APM defines the term as: "A negative risk event; a risk event that if it occurs will have a downside/ detrimental effect on one or more objectives." The possible delay has a detrimental objective impact. A completed saving, accepted deliverable and planned meeting do not constitute that uncertain negative event.

    Reference: APM Project Management Glossary — Threat

  4. 4In the initiation of risk management, what are project objectives?

    1. A.Predetermined results towards which effort is directedCorrect answer: A
    2. B.The current contents of the risk action log
    3. C.The uncertainties accepted without further action
    4. D.The methods used to rank threats by importance

    Explanation: APM states: "A generic term for predetermined results towards which effort is directed. Objectives may be defined in terms of outputs, outcomes and/or benefits." Objectives state intended results, rather than records, uncertainties or ranking methods.

    Reference: APM Project Management Glossary — Objectives

  5. 5What does a risk management plan define for a project?

    1. A.The final financial result after all risks have closed
    2. B.The hierarchy of deliverables to be handed over
    3. C.How risk management will be implemented for the projectCorrect answer: C
    4. D.The supplier's standard price for responding to all threats

    Explanation: APM states: "A document defining how risk management is to be implemented in the context of the particular project concerned." The plan specifies the project's approach to implementing risk management, not final accounts, deliverables or prices.

    Reference: APM Project Management Glossary — Risk management plan

  6. 6An organisation is introducing PRAM but staff are unfamiliar with quantitative models. What introduction does the mini guide recommend?

    1. A.Begin by requiring the same quantitative model on every pilot project
    2. B.Begin gradually while developing organisational acceptabilityCorrect answer: B
    3. C.Choose the software platform before agreeing the risk process
    4. D.Use a full quantitative report as the prerequisite for initial training

    Explanation: APM states: "It is recommended that new practitioners start slowly, perhaps even ignoring this ‘sub-stage’, until a climate of acceptability has been developed for project risk analysis and management in the organisation." Gradual adoption builds acceptance. Uniform full modelling, software-first selection and a modelling-report prerequisite put sophistication ahead of the recommended introduction.

    Reference: APM Project Risk Analysis and Management Mini Guide – web edition — 3. What is involved? – Quantitative analysis

  7. 7Which technique examines strengths, weaknesses, opportunities and threats?

    1. A.SWOT analysisCorrect answer: A
    2. B.Delphi technique
    3. C.Monte Carlo simulation
    4. D.Sensitivity analysis

    Explanation: APM states: "A technique used to identify the strengths, weaknesses, opportunities and threats inherent in a project." SWOT is the four-part examination. Delphi develops expert consensus; Monte Carlo combines uncertainty; sensitivity examines changed inputs.

    Reference: APM Project Management Glossary — SWOT (analysis)

  8. 8A supplier has not qualified a component; qualification might fail and delay delivery. Which description correctly separates cause, risk event and effect?

    1. A.Cause: delayed delivery; event: unqualified component; effect: possible failure
    2. B.Cause: unqualified component; event: possible qualification failure; effect: delayed deliveryCorrect answer: B
    3. C.Cause: possible failure; event: delayed delivery; effect: unqualified component
    4. D.Cause: possible qualification failure; event: unqualified component; effect: delayed delivery

    Explanation: APM states: "separating causes (facts now), from risk events (situations that may occur), from effects (that have an impact on one or more of the project measures)." The present unqualified state is the cause, possible future failure the event and delayed delivery the objective effect. A reverses cause/effect, C moves the future event into cause and the current state into effect, and D swaps cause and event.

    Reference: APM What Is Risk Management? — What is risk analysis?

  9. 9A modeller changes one input and observes how the project outcome changes. Which technique is being used?

    1. A.Sensitivity analysisCorrect answer: A
    2. B.Delphi technique
    3. C.SWOT analysis
    4. D.Risk interviewing

    Explanation: APM states: "An investigation of the effect on the outcome of changing parameters or data in procedures or models." Sensitivity analysis examines outcome changes when inputs vary. Consensus, SWOT and interviews serve different purposes.

    Reference: APM Project Management Glossary — Sensitivity analysis

  10. 10A team changes the design so a particular threat can no longer affect the project. Which response is this?

    1. A.Reduce
    2. B.Accept
    3. C.Fallback
    4. D.AvoidCorrect answer: D

    Explanation: APM states: "A response to a threat that eliminates its probability or impact on the project." Avoidance eliminates the threat's probability or impact. Reduction lowers exposure without necessarily eliminating it; acceptance and fallback do not remove it now.

    Reference: APM Project Management Glossary — Avoid

Exam Review

About APM Project Risk Management Single Subject Certificate Level 1

APM Project Risk Management Single Subject Certificate Level 1 · GB

Key exam facts

Provider
Association for Project Management (APM), the chartered body for the project profession, owns and runs the examination; accredited training providers offer courses and exam arrangements.
Format
Knowledge examination with compulsory multiple-choice questions; available as an open online exam.
Exam questions
Total questions: 60.
Time limit
One hour of examination time; approved reasonable adjustments may provide extra time.
Passing score
60% of total available marks; each question carries a maximum of one mark. APM notes that the pass mark may change on recommendation of its Senior Examiner Team.
Exam fee
Open online Level 1 examination, GBP including VAT: members £260.40; non-members £278.40; resit £207.60. Training course fees are separate.

Topics covered

  • General

  • Benefits

  • Principles

  • Process

    • Initiate
    • Identify
    • Assess
    • Plan responses
  • Organisation and control

  • Behaviour

  • Application

  • Risk identification techniques

  • Qualitative risk assessment

  • Quantitative risk assessment

  • Risk response

How to prepare

Work through the topics, read the explanation after each answer, and revisit the areas where you miss questions. Use the official outline and reference materials below to guide your study.

These independent practice questions are not actual exam items and do not guarantee a passing result.

Frequently asked questions

What is the exam format?

Knowledge examination with compulsory multiple-choice questions; available as an open online exam.

How many questions are on the exam?

Total questions: 60.

How long is the exam?

One hour of examination time; approved reasonable adjustments may provide extra time.

What is the passing score?

60% of total available marks; each question carries a maximum of one mark. APM notes that the pass mark may change on recommendation of its Senior Examiner Team.

How much does the exam cost?

Open online Level 1 examination, GBP including VAT: members £260.40; non-members £278.40; resit £207.60. Training course fees are separate.

Official sources and references

Confirm current exam arrangements with the exam provider.